2,750

yards of new tunnels

90,000

cubic metres of reinforced concrete

11,000

tonnes of iron

TECHNICAL DESCRIPTION

 
The new Turin-Ceres railway connection, with a total length of 3701 yards, runs entirely underground. The work includes the demolition of a viaduct and a flyover, the redevelopment of the market square and the creation of a road underpass, as well as a new sewage network made up of approx. 2080 yards of tunnel at a depth of about 15 yards.

cmb-infrastrutture-infrastructures-torino-ceres-railway-connection-infographic

The figures for the Turin-Ceres line

 
A look at the new railway tunnel, with an underground stop and works on the surface to build an integrated infrastructure system. The project includes a solution to interference with the sewer system, with excavation methods consistent with the length of the sections.

Value of the works
115,000,000 euro

Client
SCR Piemonte Spa

Role in the project
Contractor (Consortile Cervit)

Completion time
2019 – in progress

">